It is necessary to reschedule the power shutdown from Saturday, October 15th to Sunday, October 16th from 6:00 a.m. to 4:00 p.m. This shutdown is required to upgrade one of the transformers in the campus substation.
The following buildings will be affected by this shutdown:
Alumni Hall, Dillingham, East Tower, Fitness Center, Friends, Hill Center, Job Hall, Muller, Textor, Tower Club, Towers Dining, and Smiddy Hall. Power in Ford Hall, Gannett, and Whalen will be interrupted for a very brief period of time on the morning of the 16th.
Please turn off all computers and printers prior to the shutdown. As always, the Physical Plant staff will be on duty during this interruption to ensure all systems resume their normal function.
If you have any questions, please call the Physical Plant office at 4-3225.
Thank you for your cooperation!