The following Summer Construction Projects are to begin:
Construction will be taking place: Electrical Infrastructure- Substation/Underground
Starting: May 18, 2006
Ending: Fall 2006
Possible Conditions resulting from this project:
Areas off line: Certain roadways around campus
Noise levels Low
Electrical Interruptions None
ITS Interruptions None
Plumbing Interruptions None
Heating or coolng interruptions None
Change in traffic patterns Minimal
Traffic Delays Minimal
Construction will be taking place: Terrace Electrical Upgrade- Phase II
Starting: May 18, 2006
Ending: July 14, 2006
Possible Conditions resulting from this project:
Areas off line: Terraces
Noise levels Moderate
Electrical Interruptions Complete
ITS Interruptions Entire area
Plumbing Interruptions None
Heating or coolng interruptions No heat
Change in traffic patterns Closed
Traffic Delays None
Construction will be taking place: CNS 206 Scale UP Program- 2nd floor classrooms
Starting: May 18, 2006
Ending: August 11, 2006
Possible Conditions resulting from this project:
Areas off line: CNS 206,208,209 & 210
Noise levels Low to high
Electrical Interruptions Minimal
ITS Interruptions None
Plumbing Interruptions Minimal
Heating or coolng interruptions None
Change in traffic patterns None
Traffic Delays None
Construction will be taking place: Boothroyd Hall- Room Renovations
Starting: May 18, 2006
Ending: July 31, 2006
Possible Conditions resulting from this project:
Areas off line: Boothroyd Hall
Noise levels Moderate to high
Electrical Interruptions Shut down for new transformer
ITS Interruptions To Boothroyd Hall
Plumbing Interruptions To Boothroyd Hall
Heating or coolng interruptions To Boothroyd Hall
Change in traffic patterns Closed
Traffic Delays None
Construction will be taking place: Residential Hall Upgrades- Carpeting & Painting
Starting: May 18, 2006
Ending: July 2006
Possible Conditions resulting from this project:
Areas off line: At certain times (as schedule) the Terraces, Lyons, Bogart, Hillard, Rowland Halls & College Circle
Noise levels Low
Electrical Interruptions None
ITS Interruptions None
Plumbing Interruptions None
Heating or coolng interruptions None
Change in traffic patterns None
Traffic Delays None
Construction will be taking place: Roy Park Digital Classrooms- Renovations to Room 185A
Starting: May 18, 2006
Ending: July 2006
Possible Conditions resulting from this project:
Areas off line: Roy Park Room 185A
Noise levels Low to high
Electrical Interruptions None
ITS Interruptions New
Plumbing Interruptions 1 shutdown
Heating or coolng interruptions Room 185A
Change in traffic patterns None
Traffic Delays None
Construction will be taking place: Emerson Hall- Security Screens
Starting: May 2006
Ending: Fall 2006
Possible Conditions resulting from this project:
Areas off line: 1st floor Emerson Hall
Noise levels Low
Electrical Interruptions None
ITS Interruptions None
Plumbing Interruptions None
Heating or coolng interruptions None
Change in traffic patterns None
Traffic Delays None
Construction will be taking place: Terrace Paving- Replace sidewalks at the Terraces
Starting: July 20, 2006
Ending: August 11, 2006
Possible Conditions resulting from this project:
Areas off line: Terrace parking lots
Noise levels High
Electrical Interruptions None
ITS Interruptions None
Plumbing Interruptions None
Heating or coolng interruptions None
Change in traffic patterns Closed
Traffic Delays During pavement deliveries