Paving Update for T-Lot, Flora Brown Drive and F-Lot

07/15/11

Contributed by Crystal Young

Please be aware of paving taking place in the following areas during the next 2 weeks:

Monday, July 18th, paving will begin in T-Lot (next to Terrace Dining) as well as Flora Brown Drive to the Terrace Circle.

Thursday, July 21st, the upper section of F-Lot (south side) will be paved.  This should be completed by Tuesday, July 26th.