Job Hall Moves Up the Wi-Fi Project Schedule

02/25/15

Contributed by Matt Gorney

In order to accommodate the newly moved academic spaces in Job Hall, the ITS Wi-Fi Project team has decided to move this building up the schedule queue, to an April timeframe.  

This change does not put the project in any jeopardy of completing by our estimated June completion time.  It was simply moved up in an effort to complete academic spaces, and April is the most optimal time to do this work.

You can see the full schedule of buildings with their current status at the following link: 
https://www.ithaca.edu/its/services/wireless/campusproject2014/schedule/